What is being built.

Major projects and their latest reported status. An announcement is not a finished project, so each shows its status and the date of its evidence.

Government staff quarters under construction in Amaravati, August 2024. Photo: iMahesh, CC BY-SA 4.0, via Wikimedia Commons.

Overall physical progress of capital works as of 28 June 2026 (reported)
Actual 31.9% Planned 53.8%

Source: reported APCRDA construction review. The shortfall is the gap between the bar and the planned marker.

Latest official updates

All updates →

Checking official sources…

Loading official updates…

Cosmos summarises public sources. Always check the original source before making a decision, and read dates as the date of the evidence, not of today.

Tendering; approval pending

Outer Ring Road

NHAI has invited bids for a 195 km, six-lane, access-controlled Outer Ring Road around Amaravati in four packages worth about ₹11,538 crore, with bids due on 18 November. Reports say formal Union Cabinet approval was still pending. Estimates of the total project cost vary widely between sources.

Sources: The News Minute (October 2026)

Behind plan

Construction behind plan in mid-2026 review

A reported APCRDA review as of 28 June 2026 put overall physical progress at 31.9% against a planned 53.8%. The state government has said Phase I remains targeted for completion in 2027; earlier targets of mid-2026 were not met.

Sources: BizAndhra (July 2026) · AIR News (newsonair.gov.in) (4 April 2026)

Under construction

Secretariat towers, Assembly and High Court

The state's minister for municipal administration said in March 2026 that construction of the five Secretariat towers was progressing quickly, after rain delayed work for about four months the previous year. The Assembly and High Court buildings are also reported to be under construction. Cosmos has not found an official completion date.

Sources: The Hans India (March 2026) · AIR News (newsonair.gov.in) (22 February 2026)

Under construction

Amaravati Quantum Valley

Union Science and Technology Minister Dr Jitendra Singh and Chief Minister N. Chandrababu Naidu laid the foundation stone for the Amaravati Quantum Valley on 7 February 2026, at Uddandarayunipalem in Thullur mandal according to news reports. IBM said it planned to commission an IBM Quantum System Two there by September 2026. As of 13 November 2026, Cosmos has not found confirmation that it has been commissioned.

Sources: AIR News (newsonair.gov.in) (7 February 2026) · Deccan Herald (7 February 2026) · ThePrint (PTI) (2026)

Under way

Second phase of land pooling

The state Cabinet approved a second phase of land pooling of about 16,666 acres across seven villages (Vaikuntapuram, Pedda Madduru, Endrai, Karlapudi, Vaddamanu, Harishchandrapuram and Peddaparimi), and the process began on 7 January 2026. The first phase pooled about 34,000 acres. Opposition parties have criticised the second phase; the government says farmers are participating voluntarily.

Sources: Siasat (PTI) (November 2025) · Siasat (PTI) (7 January 2026)

Capital construction relaunched

On 2 May 2025 the Prime Minister laid foundation stones for and launched projects worth about ₹58,000 crore in Andhra Pradesh, including the relaunch of construction of the Amaravati capital city. Reported Amaravati works include the Assembly, Secretariat and High Court buildings and housing.

Sources: ThePrint (PTI) (2 May 2025) · Business Standard (2 May 2025)

₹11,000 crore loan agreement with HUDCO

The Andhra Pradesh Capital Region Development Authority (APCRDA) and HUDCO signed a ₹11,000 crore loan agreement for Amaravati construction on 16 March 2025.

Sources: ThePrint (PTI) (16 March 2025)

World Bank approves $800 million

The World Bank approved an $800 million loan for the development of Amaravati on 19 December 2024. Reports describe a 29-year term including a six-year grace period.

Sources: Deccan Herald (19 December 2024) · ThePrint (PTI) (20 December 2024)

Asian Development Bank approves $788.8 million

The Asian Development Bank approved a results-based loan of about $788.8 million to Andhra Pradesh to develop Amaravati. Together with the World Bank, reported multilateral funding for Phase I is about $1.6 billion.

Sources: Business Standard (12 December 2024)

Approved

New railway line through Amaravati

The Union Cabinet approved a new 57 km railway line from Errupalem to Namburu via Amaravati on 24 October 2024, at a reported cost of about ₹2,245 crore, with nine new stations and a completion period of five years. The state later approved pooling about 6,212 acres of land for the line. Cosmos has not found a construction progress update.

Sources: Press Information Bureau (24 October 2024) · ThePrint (PTI) (24 October 2024) · The South First (2025)

Sources last checked 13 November 2026. Spotted something out of date? Tell us.